Overview
The Azule onshore gas treatment plant integrates gas from two offshore platforms into an onshore processing facility. The project uses ABB 800xA as the supervisory DCS and requires tight integration with vendor-supplied ICSS, Fire & Gas (FGS) and ESD systems. I joined during commissioning and led a focused engineering recovery to bring key systems to operational readiness for Early Gas.
Technical highlights
- Redesigned control panels to resolve voltage incompatibilities between field and panels
- Implemented structured-text voting logic (1oo2, 2oo3 & custom votes) inside 800xA
- Installed DTMs for PST on SDV valves and enabled valve diagnostics
- Rebuilt operator graphics to match validated P&IDs
- Created Modbus database & mapping for motors, VSDs, and vendor skids
- Configured LV/MV switchgear network switches and assisted vendors with Modbus alignment
My Scope (detailed)
Panel Redesign & Power Segregation
Addressed mismatched voltages observed at site by redesigning marshalling, power distribution and termination strategies to protect field devices and ensure signal integrity.
DTM & Valve Integration
Installed and validated DTMs for PST on SDVs to allow on-line valve health checks and enable predictive maintenance workflows.
Modbus Database & Motor Control
Built the Modbus register database in 800xA, implemented mapping for motor telemetry and control, and developed control logic for motor & VSD sequences.
Structured Text Voting Logic
Authored robust voting functions in ST for ESD/FGS logic — central to safe plant behaviour under multiple-fault scenarios. Implemented reusable vote blocks with diagnostics.
HMI Graphics Rebuild
Recreated operator graphics directly from validated P&IDs, improving operator clarity and reducing alarm overload during plant bring-up.
Network & Vendor Support
Configured LV/MV switchgear switches (VLANs, redundancy, port security) and assisted vendors in correcting Modbus maps to ensure consistent communications.
Challenges & Solutions
Outcome & Status
Early Gas operations were achieved in 2025 following targeted hardware fixes, voting logic implementation and Modbus alignment. The project remains in commissioning and final completion is planned for early 2026. The work has stabilised DCS behaviour, improved safety logic determinism and ensured robust communications across vendor systems.